Home » Other » Training & Certification » ocp qn. for performance tuning : Resource Manager rules
ocp qn. for performance tuning : Resource Manager rules [message #168551] Thu, 20 April 2006 22:57
tridentadm
Messages: 142
Registered: March 2006
Senior Member
Which of the following Resource Manager rules must be validated with the DBMS_RESOURCE_MANAGER.validate_pending_area procedure? (Choose three.)

A. The plan must have a directive for OTHER_GROUPS.
B . Each subplan must reference the top-level plan's consumer group.
C. Referenced subplans and/or consumer groups must exist.
D. No subplan loops.
E . The plan must have a directive for SYSTEM_GROUP.


Previous Topic: Reg Triggers-Which is the correct answer
Next Topic: Data warehousing Certification and Interview Questions
Goto Forum:
  


Current Time: Thu Mar 28 05:48:06 CDT 2024